Skip to main content

Language: English / Gàidhlig

Loading…

Chamber and committees

Questions and answers

Parliamentary questions can be asked by any MSP to the Scottish Government or the Scottish Parliamentary Corporate Body. The questions provide a means for MSPs to get factual and statistical information.

  • Written questions must be answered within 10 working days (20 working days during recess)
  • Other questions such as Topical, Portfolio, General and First Minister's Question Times are taken in the Chamber

Urgent Questions aren't included in the Question and Answers search.  There is a SPICe fact sheet listing Urgent and emergency questions.

Find out more about parliamentary questions

Filter your results Hide all filters

Dates of parliamentary sessions
  1. Session 1: 12 May 1999 to 31 March 2003
  2. Session 2: 7 May 2003 to 2 April 2007
  3. Session 3: 9 May 2007 to 22 March 2011
  4. Session 4: 11 May 2011 to 23 March 2016
  5. Session 5: 12 May 2016 to 5 May 2021
  6. Current session: 12 May 2021 to 2 July 2024
Answer status
Question type

Displaying 1771 questions Show Answers

|

Question reference: S6W-12893

  • Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
  • Date lodged: Tuesday, 06 December 2022
  • Current Status: Answered by Michael Matheson on 8 December 2022

To ask the Scottish Government, further to the answer to question S6W-10006 by Michael Matheson on 23 August 2022, whether it is the case that it has now assessed the cost of achieving net zero greenhouse gas emissions by 2045, and, if it is not the case, when the full costing is expected to be completed.

Question reference: S6W-12576

  • Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
  • Date lodged: Tuesday, 29 November 2022
  • Current Status: Answered by Michael Matheson on 8 December 2022

To ask the Scottish Government what consideration it has given to introducing a Net-Zero Ports and Infrastructure Programme fund, which has been identified by Scottish Renewables as key for supporting strategic port infrastructure and developing offshore renewable projects.

Question reference: S6W-12640

  • Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
  • Date lodged: Wednesday, 30 November 2022
  • Current Status: Answered by Mairi McAllan on 8 December 2022

To ask the Scottish Government, further to the answer to question S6W-12081 by Mairi McAllan on 24 November 2022, when it will issue the release on its attendance and expenses incurred at COP27.

Question reference: S6W-12655

  • Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
  • Date lodged: Wednesday, 30 November 2022
  • Current Status: Answered by John Swinney on 8 December 2022

To ask the Scottish Government, following the announcement that the MV Glen Sannox will initially operate using a single diesel fuel system, as opposed to the planned dual-fuel LNG system, how much is expected to be saved as a result in (a) design, (b) manufacture and build and (c) ongoing fuelling costs, and how will any money saved now be spent.

Question reference: S6O-01692

  • Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
  • Date lodged: Wednesday, 07 December 2022
  • Current Status: Taken in the Chamber on 15 December 2022

To ask the Scottish Government whether it considers hydrogen as an alternative to natural gas to be a viable solution to decarbonising heat in homes.

Question reference: S6W-12572

  • Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
  • Date lodged: Monday, 28 November 2022
  • Current Status: Answered by Jenny Gilruth on 7 December 2022

To ask the Scottish Government, further to the answer to question S6W-12086 by Jenny Gilruth on 22 November 2022, whether it will provide the information requested regarding when it originally planned to begin fully dualling the A96, and what impact its consultation has had on that start date.

Question reference: S6W-12357

  • Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
  • Date lodged: Friday, 25 November 2022
  • Current Status: Answered by Mairi McAllan on 6 December 2022

To ask the Scottish Government, in relation to the proposed Land Reform Bill, whom it has identified as the "key stakeholders" for the purpose of policy development, and what engagement is taking place with those stakeholders.

Question reference: S6W-12580

  • Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
  • Date lodged: Tuesday, 29 November 2022
  • Current Status: Answered by Tom Arthur on 5 December 2022

To ask the Scottish Government whether it will extend the 90% non-domestic rates relief for district heating networks powered by renewables until 2035.

Question reference: S6W-12291

  • Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
  • Date lodged: Thursday, 17 November 2022
  • Current Status: Answered by Mairi McAllan on 2 December 2022

To ask the Scottish Government what meetings took place with any community organisations regarding the Glenprosen estate (a) purchase and (b) change of use.  

Question reference: S6W-12288

  • Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
  • Date lodged: Thursday, 17 November 2022
  • Current Status: Answered by Mairi McAllan on 1 December 2022

To ask the Scottish Government whether it will provide (a) minutes for and (b) a list of, any (i) consultation meetings and (ii) consultees with whom discussions took place in relation to the purchase of the Glenprosen estate.