- Asked by: Lewis Macdonald, MSP for North East Scotland, Scottish Labour
-
Date lodged: Tuesday, 12 January 2016
-
Current Status:
Answered by Shona Robison on 26 January 2016
To ask the Scottish Government, further to the answer to question S4W-28956 by Shona Robison on 6 January 2016, if none of the additional £41.6 million being spent on the procurement of the new IT system is as a result of the system failure in October 2015, (a) what the reason is for the additional expenditure and (b) whether it will provide a breakdown of what the additional money is being spent on.
Answer
The delay of the implementation of the Future Programme from the original business case until October 2015 cost an additional £41.6 million which is broken down as follows:
Double running of legacy and new system
|
£11.7 million
|
Contract costs
|
£14.3 million
|
Implementation costs
|
£8 million
|
Scope and re-design costs
|
£7.6 million
|
Total additional costs
|
£41.6 million
|
The delay from October 2015 until the summer of 2016 will add a further £7.6 million of costs to the project. The main reasons for this further increase is additional double running costs and the costs associated with preparing for the 2016 re-launch.
- Asked by: Lewis Macdonald, MSP for North East Scotland, Scottish Labour
-
Date lodged: Thursday, 14 January 2016
-
Current Status:
Answered by Annabelle Ewing on 25 January 2016
To ask the Scottish Government how many modern apprentices in the oil and gas sector have been made redundant each year, and what information it has regarding how many subsequently found (a) a new position in the sector, and at what level, (b) a modern apprenticeship elsewhere and (c) other employment or training.
Answer
The Scottish Government does not hold this information centrally. I will ask the Chief Executive of Skills Development Scotland to write to you with the information you have requested.
- Asked by: Lewis Macdonald, MSP for North East Scotland, Scottish Labour
-
Date lodged: Thursday, 14 January 2016
-
Current Status:
Answered by Annabelle Ewing on 25 January 2016
To ask the Scottish Government, further to the answer to question S4W-27023 by Roseanna Cunningham on 26 August 2015, whether it will provide an update on how many modern apprentices in the offshore oil and gas sector have been hired using the Adopt an Apprentice scheme.
Answer
As explained in the response to S4W-27023, the figures for the enhanced oil and gas Adopt an Apprentice offer relate to the sector as a whole; it is not possible to provide figures relating to offshore employers only.
As at 19 January 2016, Skills Development Scotland has approved 21 applications for support through the enhanced Adopt an Apprentice offer.
- Asked by: Lewis Macdonald, MSP for North East Scotland, Scottish Labour
-
Date lodged: Tuesday, 12 January 2016
-
Current Status:
Answered by John Swinney on 15 January 2016
To ask the Scottish Government what percentage of the average local authority revenue support per capita Aberdeen City Council will be given in 2016-17.
Answer
In 2016-17, Aberdeen City Council's per capita revenue grant support from the Scottish Government will be 85% of the adjusted Scottish average figure.
- Asked by: Lewis Macdonald, MSP for North East Scotland, Scottish Labour
-
Date lodged: Tuesday, 12 January 2016
-
Current Status:
Answered by John Swinney on 15 January 2016
To ask the Scottish Government whether it plans to apply a total local authority revenue support funding floor in the review period beginning April 2016.
Answer
The Scottish Government has no plans to remove the total local authority revenue support funding floor, which provides funding protection and stability for all local authorities, from future local government finance settlements.
- Asked by: Lewis Macdonald, MSP for North East Scotland, Scottish Labour
-
Date lodged: Tuesday, 12 January 2016
-
Current Status:
Answered by John Swinney on 15 January 2016
To ask the Scottish Government what percentage of the average local authority revenue support per capita Aberdeen City Council has received in each year since 2011-12.
Answer
In 2011-12 Aberdeen City Council's per capita revenue grant support from the Scottish Government was 83.4% of the Scottish average figure. Following the introduction of the new funding floor which guarantees all local authorities 85% of the Scottish average revenue funding per capita, Aberdeen City Council's revenue funding has been maintained at 85% of the adjusted Scottish average.
- Asked by: Lewis Macdonald, MSP for North East Scotland, Scottish Labour
-
Date lodged: Friday, 11 December 2015
-
Current Status:
Answered by Shona Robison on 6 January 2016
To ask the Scottish Government, further to the answer to question S4W-28718 by Shona Robison on 10 December 2015, how much it has spent on running the old NHS 24 IT system since the new system failed in October 2015 in addition to the £117.4 million that is being spent on the procurement of the new IT system.
Answer
The £117.4 million already includes an element of planned double running costs for the existing system as part of a phased transition to the new system. The additional cost of double running the existing system to the end of March 2016 is £1.0 million.
- Asked by: Lewis Macdonald, MSP for North East Scotland, Scottish Labour
-
Date lodged: Friday, 11 December 2015
-
Current Status:
Answered by Shona Robison on 6 January 2016
To ask the Scottish Government, further to the answer to question S4W-28718 by Shona Robison on 10 December 2015, how much of the money spent on the procurement of the new IT system for NHS 24 was paid to external consultants.
Answer
Of the £117.4 million total, contractor implementation costs are £36.8 million.
- Asked by: Lewis Macdonald, MSP for North East Scotland, Scottish Labour
-
Date lodged: Friday, 11 December 2015
-
Current Status:
Answered by Shona Robison on 6 January 2016
To ask the Scottish Government, further to the answer to question S4W-28719 by Shona Robison on 10 December 2015, on what dates the new IT system for NHS 24 was tested prior to going live and what the results were.
Answer
The new system was tested thoroughly and robustly over a period of time from March through to September 2015 in advance of the October implementation.
- Asked by: Lewis Macdonald, MSP for North East Scotland, Scottish Labour
-
Date lodged: Friday, 11 December 2015
-
Current Status:
Answered by Shona Robison on 6 January 2016
To ask the Scottish Government, further to the answer to question S4W-28718 by Shona Robison on 10 December 2015, how much of the additional £41.6 million spent on the procurement of the new IT system for NHS 24 is a direct result of the system failure in October 2015.
Answer
None of the £41.6 million spent on the new system is a result of the pause to the phased implementation from October 2015.