he information with regard to costs is shown in the following table. These are estimated costs as at 1 September 2004, exclude VAT, and may be subject to change as schemes progress. The table, as published in response to S2W-9859, already shows the position with respect to draft and finalised roads orders, and indicates where public inquiries are known or expected. Again, this information is subject to change over time. Progress on schemes is subject to completion of the necessary statutory procedures, and the availability of finance.
Road | Scheme | Summary Description | Est. Cost (£M) @1/9/04 | Estimated Start Date | Estimated Completion Date | Notes |
A1 | Thistly Cross to Bowerhouse. | Construction of new 0.8km dual carriageway | 2.86 | Under construction | Q1-2005-06 | Final planned section of dualling of A1 |
A68 | Soutra South to Oxton. | Improve Southbound overtaking & Oxton junction | 4.30 | Q1-2006-07 | Q1-2007-08 | Consultant appointed - In preparation |
A68 | Pathhead to Tynehead Junction. | Provide 1.9km of improved overtaking opportunities | 7.76 | Q1-2006-07 | Q1-2007-08 | Consultant appointed - In preparation |
A7 | Auchenrivock. | Improvement of 2.3km single carriageway to provide overtaking opportunities | 4.70 | Q4-2005-06 | Q4-2006-07 | Consultant appointed - In preparation |
A7 | Glenmayne to Yair. | Improvement of 1.7km single carriageway to provide overtaking opportunities | 4.90 | Q3-2005-06 | Q3-2006-07 | Consultant appointed - In preparation |
A75 | Cairntop to Barlae. | 2.2km Overtaking scheme | 4.60 | Q4-2005-06 | Q3-2006-07 | Consultant appointed - In preparation |
A75 | Newton Stewart | To provide guaranteed westbound overtaking on existing incline. | 1.84 | Q2-2005-06 | Q4-2005-06 | Consultant appointed - In preparation |
A75 | Barfill to Bettyknowes. | Provision of overtaking opportunities over 1.2km section. | 2.59 | Q1-2005-06 | Q1-2006-07 | Consultant appointed - In preparation |
A75 | Planting End to Drumflower | Provision of 1.5km overtaking opportunities. | 2.84 | Q2-2005-06 | Q4-2005-06 | Consultant appointed - In preparation |
A75 | Dunragit Re‑alignment. | Rail bridge replacement and provision of 3km of overtaking opportunities. | 10.30 | Oct 2006 | Dec 2007 | Consultant appointed - In preparation |
A75 | Hardgrove to Kinmount. | Provision of 4km of safer overtaking opportunities | 6.20 | Nov 2006 | Nov 2007 | Consultant appointed - In preparation |
A76 | Gateside (2) | Study to identify a 2km section of A76 North Sanquhar for overtaking section. | n/a | Study under way | | |
A76 | Glenairlie. | Provision of a 2km climbing lane. | 3.50 | Q4-2005-06 | Q4-2006-07 | Consultant appointed - In preparation |
A77 | Maybole Bypass | Appraisal to identify solutions to transport problems on the A77 through Maybole. | n/a | Public consultation under way | | Consultant appointed |
A77 | Park End to Bennane WS2 | Provision of overtaking opportunity. | 2.70 | Q4-2005-06 | tba | Consultant appointed - In preparation |
A77 | Haggstone Climbing Lane. | Provision of northbound climbing lane. | 3.57 | Q3-2005-06 | tba | Consultant appointed - In preparation |
A77 | Glen App WS2+1. | Provision of overtaking opportunity. | 2.62 | Q1-2006-07 | tba | Consultant appointed - In preparation |
A77 | Drummuckloch to Innermessan. | Provision of overtaking opportunity. | 3.20 | Q4-2005-06 | tba | Consultant appointed - In preparation |
A77 | Ardwell to Slockenray WS2. | Provision of overtaking opportunity. | 2.06 | Q1-2006-07 | tba | Consultant appointed - In preparation |
A77 | Symington and Bog End Toll | Junction improvements | n/a | tba | tba | Public exhibition of revised proposals held |
A78 | 3 Towns Bypass (Ardrossan, Saltcoats & Stevenson). | 5km of 2-lane dual carriageway road and 1.4km of single carriageway road with climbing lane. Roundabouts at each end to connect the bypass with existing trunk road, and two intermediate junctions with local roads. | 30.30 | Under construction | Dec 2004 | |
A80 | Auchenkilns Junction | Grade separated interchange on the A80. | 22.80 | Under construction | Sep 2005 | |
A80 | Allandale Park & Ride | Feasibility study report | 0.45 | In preparation | Nov 2004 | Study only |
A82 | Route Action Plan Study. | Production of a strategy for improving operation and safety over this 154km route | 0.35 | Traffic surveys and consultation under way | | Study report Q3 2005-06 |
A830 | Arisaig to Loch Nan Uamh. | Upgrade of 7km of single track road on A830 strategic route | 14.25 | Q1-2005-06 | tba | Draft Orders published |
A876 | Kincardine Eastern Link Road. | Construction 2km of new wide single carriageway Eastern Link road to remove traffic from Kincardine village. | 9.80 | 5-2003 | 3-2005 (includes landscaping) | Road opened 5 July 2004 - 6 months ahead of schedule |
A876 | Kincardine Bridge. | Construction of 8.1 km access roads and new bridge upstream of existing crossing, plus refurbishment of existing bridge structure. | 89.50 | Q4-2005-06 | Q2-2008-09 | Draft orders published - public local inquiry Q3-2004-05 |
A9 | Route Improvement Strategy. | Consider need to upgrade 35 km sections of A9 north of Perth. | 0.35 | Study in preparation | | |
A9 | Ballinluig Junction | Construction of a grade separated junction to improve road safety. | 7.90 | Q4-2005-06 | Q2-2007-08 | Consultant appointed - In preparation |
A9 | Helmsdale to Ord of Caithness - Phase 2 | 1.8km Road upgrading scheme to remove poor geometry and narrow widths of existing road | 4.50 | Q3-2005-06 | tba | Road Orders made |
A9 | Crubenmore Extension. | 1.9km Extension of existing short length of dual carriageway. | 2.43 | tba | tba | Consultant appointed - In preparation |
A9 | Kincraig to Dalraddy | Provision of guaranteed overtaking opportunities over 4km | 1.94 | tba | tba | Consultant appointed - In preparation |
A90 | Aberdeen Western Peripheral Route. | To provide a 29km bypass to Aberdeen | 120.00 | Oct 2007 | Oct 2010 | Scheme in preparation. Draft orders to be published 2005 |
A90 | Glendoick. | 4th Grade separated interchange on the A90 trunk road between Perth and Dundee to improve road safety | 5.90 | Q3-2005-06 | Q3-2006-07 | Consultant appointed - In preparation |
A90 | Kinfauns. | Last grade separated interchange on the A90 trunk road between Perth and Dundee | 5.10 | Q3-2005-06 | Q3-2006-07 | Consultant appointed - In preparation |
A90 | Balmeddie - Tipperty | Multimodal appraisal of the single carriageway section of the A90 | 0.10 | Q1-2002-03 | Q2-2004-05 | Study report |
A96 | Threapland. | 0.75km Junction improvement and re-alignment to improve visibility. | 0.60 | tba | tba | Early preparation |
A96 | Dalnies | Provision of 1.1km guaranteed overtaking opportunities (WS2+1). | 0.51 | tba | tba | Early preparation |
A96 | Coachford Climbing Lane. | 2.4 km climbing lane to provide overtaking opportunities and improve safety and level of service on route. | 6.70 | Q3-2004-05 | Q4-2005-06 | Tenders received - under consideration |
A96 | Fochabers and Mosstodloch | Construction of 5km wide single carriageway to bypass the settlements of Fochabers and Mosstodloch. Side road connections are proposed at roundabouts for Mosstodloch/Baxters, Fochabers/Spey Bay, and the A98. A separate cyclepath/footpath would be provided linking Fochabers and Mosstodloch. | 15.20 | Q1-2006-07 | tba | Public Local Inquiry held Sep 2003 |
A985 | Route Action Plan. | Consider need for improvements to 19km route. | 0.35 | Study under way | | Study report Q3 2005-06 |
M74 | M74 Completion | Provision of strategic link between existing M74 and M8 to remove congestion on national network through Glasgow. Involves construction of 8.0km of 3 lane carriageway with hard shoulder and 4 key junctions. | 393.0 | Early 2006 | Late 2008 | Scheme in partnership with Glasgow City, South Lanarkshire and Renfrewshire Councils. Public Local Inquiry concluded March 2004 - report awaited. |
M74/ A725 | Raith Interchange | Junction improvement | n/a | | | Early preparation |
M77 | Malletsheugh to Fenwick. | Construction of 15.2km dual carriageway extension of motorway between Glasgow and Kilmarnock to improve road safety and remove congestion. | 84.0 | Under construction | Mar 2005 | |
M8 | Baillieston to Newhouse and associated improvements | Upgrade to motorway standard of overloaded section of the A8 and associated junctions | 125.00 | Q3-2007-08 | Q1-2010-11 | Early consultations held |
M80 | Stepps-Haggs (Phase 1) M73-Low Wood. | 4km On-line upgrade | 30.56 | Q4-2006-07 | Q2-2008-09 | Orders published. Public Inquiry to be considered |
M80 | Stepps-Haggs (Phase 2) Auchenkilns to Haggs. | 8km On-line upgrade from D2AP to D2M | 42.00 | Q2-2008-09 | Q2-2010-11 | To follow Phase 1 |
M80 | Stepps-Haggs (Phase 3) Moodiesburn Bypass. | 6km Off line new construction D2M | 63.63 | Q4-2006-07 | Q2-2008-09 | To follow Phase 1 |