- Asked by: Sarah Boyack, MSP for Lothian, Scottish Labour
-
Date lodged: Wednesday, 15 June 2011
-
Current Status:
Answered by Nicola Sturgeon on 24 June 2011
To ask the Scottish Executive what the initial estimated cost was of the new Royal Hospital for Sick Children and Department for Clinical Neurosciences in Edinburgh when the project was first signed off by ministers.
Answer
NHS Lothian submitted an initial agreement for the Royal Hospital for Sick Children in April 2006. The initial agreement for the Department of Clinical Neuroscience was submitted by NHS Lothian in June 2008.
Scottish Government approved the original outline business case for the Royal Hospital for Sick Children as a stand alone project in August 2008. Upon a review of the options available the capital cost of developing the preferred way forward at the Little France site was estimated to be £147.6 million excluding enabling works.
An outline business case for the Department of Clinical Neuroscience has not been submitted to Scottish Government for approval.
- Asked by: Sarah Boyack, MSP for Lothian, Scottish Labour
-
Date lodged: Monday, 06 June 2011
-
Current Status:
Answered by Nicola Sturgeon on 14 June 2011
To ask the Scottish Executive what discussions the Cabinet Secretary for Health, Wellbeing and Cities Strategy has had with the Scottish Futures Trust regarding the combined development of the new Royal Hospital for Sick Children and Department of Clinical Neurosciences in Edinburgh.
Answer
I have had no such discussions with the Scottish Futures Trust. NHS Lothian is receiving support and advice directly from Scottish Government Officials and the Scottish Futures Trust in the development of the project.
- Asked by: Sarah Boyack, MSP for Lothian, Scottish Labour
-
Date lodged: Monday, 06 June 2011
-
Current Status:
Answered by Nicola Sturgeon on 14 June 2011
To ask the Scottish Executive what financial assistance it will give NHS Lothian for the combined development of the new Royal Hospital for Sick Children and Department of Clinical Neurosciences in Edinburgh.
Answer
The Scottish Government's position on funding support for revenue financed projects was set out in a letter to NHS chief executives from the Director General Health and Social Care on 22 March 2011. That letter detailed those elements of unitary payments made under hub initiative Design Build Finance and Maintain projects and non-profit distributing projects that would attract Scottish Government revenue support. These arrangements state that 100% of the approved capital and financing elements, and 100% of special purpose vehicle costs and insurances would be covered by Scottish Government support. In addition, 50% of the charge relating to lifecycle maintenance will be supported. Funding support will be dependant on the approval of appropriate business cases by Scottish Government with technical and commercial input provided by the Scottish Futures Trust. In addition to support for elements of the unitary payments due, the Scottish Government will be providing capital support for those elements of enabling works and equipment contained within approved business cases.
- Asked by: Sarah Boyack, MSP for Lothian, Scottish Labour
-
Date lodged: Monday, 06 June 2011
-
Current Status:
Answered by Nicola Sturgeon on 14 June 2011
To ask the Scottish Executive what support it will give NHS Lothian for the combined development of the new Royal Hospital for Sick Children and Department of Clinical Neurosciences in Edinburgh.
Answer
The Scottish Government is fully committed to the delivery of the combined development of the new Royal Hospital for Sick Children and Department of Clinical Neurosciences in Edinburgh. With support and advice from Scottish Government Officials and the Scottish Futures Trust, NHS Lothian will take the project forward as quickly as possible.
- Asked by: Sarah Boyack, MSP for Edinburgh Central, Scottish Labour
-
Date lodged: Tuesday, 08 March 2011
-
Current Status:
Answered by Roseanna Cunningham on 21 March 2011
To ask the Scottish Executive how many community projects were developed as part of the hydro-tendering process by the Forestry Commission Scotland renewables contracts announced by the Minister for Environment and Climate Change on 22 February 2011.
Answer
The results of the hydro-tendering process were announced in August and October 2010. The appointed development companies are still in the exclusivity phase and nothing has been decided as yet. Discussions are underway with some communities however.
- Asked by: Sarah Boyack, MSP for Edinburgh Central, Scottish Labour
-
Date lodged: Tuesday, 08 March 2011
-
Current Status:
Answered by Roseanna Cunningham on 21 March 2011
To ask the Scottish Executive whether the Forestry Commission Scotland renewables contracts announced by the Minister for Environment and Climate Change on 22 February 2011 give exclusive rights to the whole of the commission’s estate to those companies that won the contracts.
Answer
Forestry Commission Scotland split the geographical areas of the national forest estate into five lots.
In four of the five lots there are two companies given exclusivity for the eight month period, one dealing with schemes under 5MW site potential and the other over 5MW. In the fifth lot both development segments are dealt with by the same company. It is not intended that exclusive options will be granted on all of the forest estate in each lot at the end of the exclusivity period, instead a select list of potential sites will be taken forward and the rest of the land can be open to communities or others to take forward if possible.
- Asked by: Sarah Boyack, MSP for Edinburgh Central, Scottish Labour
-
Date lodged: Tuesday, 08 March 2011
-
Current Status:
Answered by Roseanna Cunningham on 21 March 2011
To ask the Scottish Executive whether it is aware of community renewables development scheme that have previously been worked up to the appropriate level for consideration under the provisions of the Forestry Commission Scotland renewables contracts out to tender.
Answer
Where Forestry Commission Scotland (FCS) was aware of community schemes that had started doing some preparatory work before the renewables contracts were announcement on 22 February, FCS built that knowledge into the arrangements by withholding the relevant forest blocks from the process. This has happened in the case of Dalavich, Strathyre and Mull.
- Asked by: Sarah Boyack, MSP for Edinburgh Central, Scottish Labour
-
Date lodged: Tuesday, 08 March 2011
-
Current Status:
Answered by Roseanna Cunningham on 21 March 2011
To ask the Scottish Executive on what basis it proposed the deadline of eight months from the agreement of exclusivity arrangements for communities to propose their own renewables projects on the Forestry Commission Scotland estate.
Answer
This was considered to be a reasonable time for the development partner companies to assess the potential and draw up a portfolio of suitable sites.
- Asked by: Sarah Boyack, MSP for Edinburgh Central, Scottish Labour
-
Date lodged: Tuesday, 08 March 2011
-
Current Status:
Answered by Roseanna Cunningham on 21 March 2011
To ask the Scottish Executive whether the contracts for Forestry Commission Scotland renewables contracts announced by the Minister for Environment and Climate Change on 22 February 2011 have review points where increasing payments from companies with access to the commission’s estate might be considered.
Answer
The lease arrangements are structured to provide income to Forestry Commission Scotland (FCS) based on a share of the gross income generated by specific projects or a share of net income where FCS is joint venture partner or a combination of both. Therefore if income rises due to increasing energy costs FCS will benefit.
- Asked by: Sarah Boyack, MSP for Edinburgh Central, Scottish Labour
-
Date lodged: Tuesday, 08 March 2011
-
Current Status:
Answered by Roseanna Cunningham on 21 March 2011
To ask the Scottish Executive which banks provided assistance in drawing up the contracts for the Forestry Commission Scotland’s renewables contracts announced by the Minister for Environment and Climate Change on 22 February 2011.
Answer
No banks were involved in drawing up the contracts but financial advice was provided by Grant Thornton''s Edinburgh office. However, prior to the tendering exercise FCS received advice on renewable energy developments from Fortis Bank.