Skip to main content

Language: English / Gàidhlig

Loading…

Chamber and committees

Official Report: search what was said in Parliament

The Official Report is a written record of public meetings of the Parliament and committees.  

Filter your results Hide all filters

Dates of parliamentary sessions
  1. Session 1: 12 May 1999 to 31 March 2003
  2. Session 2: 7 May 2003 to 2 April 2007
  3. Session 3: 9 May 2007 to 22 March 2011
  4. Session 4: 11 May 2011 to 23 March 2016
  5. Session 5: 12 May 2016 to 5 May 2021
  6. Current session: 12 May 2021 to 30 November 2024
Select which types of business to include


Select level of detail in results

Displaying 2151 contributions

|

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 16 June 2022

Colin Beattie

What I am saying is that, from the committee’s point of view, we can only look at evidence that we receive that we are able to scrutinise.

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 16 June 2022

Colin Beattie

I want to turn to a specific area—that of the milestone payments that totalled about £83.25 million. Paragraph 160 of the report that the Rural Economy and Connectivity Committee published back in December 2020 says:

“there is strong evidence that the contractor deliberately proceeded to construct specific sections of the vessel either out of sequence or not according to the proper specification purely as a means of triggering milestone payments on the contract.”

Paragraph 157 talks about

“the contractor progressing certain work on the vessels either incorrectly or out of sequence purely in order to trigger payments against the contract”.

10:15  

Commodore Luke van Beek also gave evidence to the committee that Ferguson’s deliberately slowed down some of the subcontracting. I am a layman, so I do not understand naval contracts, but if there are milestones at A, B and C, and the work between A and B has not been carried out and only the work at the milestone has been done in order to trigger a payment, that does not seem to me to be right.

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 16 June 2022

Colin Beattie

Given your statement that the milestone payments were payments for large equipment and so on, for example—

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 16 June 2022

Colin Beattie

Obviously, the dispute between FMEL and CMAL was significant. Was FMEL advised by the CMAL board at any point that it would resign if there was any intervention in the dispute? If so, who advised that?

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 16 June 2022

Colin Beattie

How was the £128.25 million of public money that was invested in the yard and in the construction of the ships spent?

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 16 June 2022

Colin Beattie

The committee really needs to understand that. From looking at what the REC Committee produced, its view seemed to be that the way in which the milestone payments had been done was extraordinary, because the sections were constructed out of sequence and so on. That implies to me that what I have read out was the case. Did the work between A and B take place to allow the milestone payment at B to be triggered?

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 16 June 2022

Colin Beattie

So there are large discrepancies—

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 16 June 2022

Colin Beattie

Is there any—

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 16 June 2022

Colin Beattie

So why did you accept them?